亭子桥雨水泵站建设在世界文化遗产无锡古运河河畔,规划要求严,景观标准高。泵站选址位置面积狭窄、地形复杂、地势高差不一,四周边界环境敏感。设计采用“隐蔽化”半地下式辅助用房过渡地势高差,充分利用城市土地的立体空间,泵站成形面标高设计以景观专业为先导,对检修盖板和下沉式顶板进行了巧妙的景观处理。从泵站选址、总平面设计、“隐蔽化”半地下式辅助用房、泵站工艺等方面进行了探讨。
Pavilion Bridge rainwater pump station construction in the world cultural heritage Wuxi ancient canal, planning requirements, landscape standards. Location of pumping station is narrow in area, complex terrain, topography varies, surrounded by a sensitive environment. The design adopts “hidden” semi-underground auxiliary building transitional terrain elevation, make full use of the three-dimensional space of urban land, the elevation of the molding surface of the pump station to landscape professional as the guide, the inspection cover and sunken roof were Clever landscape treatment. From the pump site selection, the total graphic design, “hidden ” semi-underground auxiliary space, pumping station technology and other aspects were discussed.