深入了解和灵活使用合同调价公式,是国际工程承包商规避风险、获得合同外收入的主要途径之一。以某国国际水电站工程为例,分析了调价公式在国际水电工程中的操作及运用技巧,比较了采用2个不同调价公式为承包商带来的不同收益,探讨了影响调价公式计算的因素,针对这些影响因素提出了相应的防范措施,为国际工程承包企业涉外工程合同管理提供借鉴。
In-depth understanding and flexible use of contract price adjustment formula is one of the main ways for international engineering contractors to avoid risks and obtain income from contracts. Taking an international hydropower project in a country as an example, this paper analyzes the operation and application skills of the price adjustment formula in international hydropower projects, and compares the different benefits brought by two different price adjustment formulas to the contractor. The factors that affect the calculation of the price adjustment formula are discussed. These influencing factors put forward corresponding precautionary measures and provide references for the management of foreign engineering contracts by international engineering contracting enterprises.