水柏铁路是我处中标的第一个国际标。线路全长5.476公里,中标总造价为5400万元。主要工程数量有:隧道三座,计2630延米;桥梁6座、共799.13米;涵洞8座,计342横延米;区间和站场土石方37.35万方;施工便道11.72公里。该上程位于云贵高原海拔1800多米的乌蒙山东部斜坡带,山高险峻、谷深坡徒,地质情况复杂。施工管区被业主和设计单位称之为“三高”(高桥墩、高边坡、高档墙)、“五
Shuibo Road is my first bid in the international standard. The total length of 5.476 kilometers line, winning the total cost of 54 million yuan. The number of major projects are: tunnels three, accounting for 2630 meters; bridges 6, a total of 799.13 meters; culverts 8, 342 meters meters; interval 37,700 square earth stations and station side; construction road 11.72 km. The upper course is located in the eastern Um Shan slope belt of over 1800 meters above sea level in the Yunnan-Guizhou Plateau with steep mountains and valleys and complex geological conditions. The construction area is called ”three highs“ by the owners and design units (Gao Qiao Pier, high slope, high-grade wall), ”five