投资50多亿元,位于五台县的山西省首座抽水蓄能电站前期工作已取得突破性进展,计划2002年正式开工建设。山西西龙池抽水蓄能电站是我省重点前期项目之一。它利用滹沱河水源提水蓄能,将使五台山出现两个人工湖泊。电站总装机容量120万kW,总投资50.1亿元。电站
With an investment of more than RMB 5 billion, the preliminary work of the first pumped-storage power station in Shanxi Province in Wutai County has achieved breakthroughs. It is planned to start construction in 2002. Shanxi Xilongchi Pumped-storage Power Station is one of the key pre-projects in our province. It utilizes the Weihe River water source for energy storage and will make Wutai Mountain appear two artificial lakes. The total installed capacity of the power station is 1.2 million kW and the total investment is 5.01 billion yuan. Power station