阐述了发展增压流化床燃烧联合循环(PFBC-CC)的必要性和我国发展PFBC-CC的基础条件。对150MWePFBC-CC商业示范电站进行了初步方案分析,为实施该项目提供了技术可行性的参考依据。图1表1参10
The necessity of the development of pressurized fluidized bed combustion combined cycle (PFBC-CC) and the basic conditions for the development of PFBC-CC in China are described. A preliminary program analysis was conducted on the 150MWe PFBC-CC commercial demonstration power station, which provided a reference for the technical feasibility of the project. Figure 1 Table 1 Reference 10