沁河杨庄改道工程的施工由河南省政府主持成立的有新乡地区、武陟县和黄河主管部门参加的工程指挥部领导,由河南黄河河务局具体承担施工组织,武陟县政府负责迁安赔偿工作。全部工程包括堤防、险工、护滩、公路桥、穿堤排灌涵洞、电力、通讯跨河线等十四个项目,计划土方350.0万米~3,石方6.6万米~3,(钅人石)与砼10180米~3,用工57.8万个,投资2906.5万元。于1981年3月正式开工,1983年6月竣工,工期两年零三个月,施工高峰人数1800人,投入各种施工机械设备399台,实际完成土方353.6万米~3,石方6.35万米~3,(钅人石)与砼11630米~3,用工58.8万个,投资2836万元,较水电部批准修正概算
Qin River Yangzhuang diversion project construction by the Henan provincial government hosted the establishment of Xinxiang area, Wulian County and Yellow River competent departments to participate in the leadership of the project headquarters, the Yellow River and Henan Bureau of Henan Province to assume the specific construction organization, Wu Li County Government is responsible for moving Ann compensation work. All the projects include fourteen projects of embankment, dangerous work, beach protection, highway bridge, embankment drainage and culverts, electric power and communication cross river. The planned earthwork is 3.5 million meters to 3 meters and the stonework is 66,000 meters to 3 meters. ) And concrete 10180 m ~ 3, employment 578,000, invest 29065000 yuan. Was officially started in March 1981, completed in June 1983, the duration of two years and three months, the peak number of 1,800 people, all kinds of construction machinery and equipment invested 399 units, the actual completion of earth 3.356 million meters 3, 63,500 cubic meters M ~ 3, (钅 man stone) and concrete 11630 m ~ 3, 588,000 workers, investment 28.36 million yuan, Ministry of Water Resources approved the revised estimates