6月12日上午9:28分,随着沙钢集团公司第一副总裁龚盛的一声令下:“6#焦炉推焦开始!”火红的焦炭从焦炉缓缓而出。霎时,鞭炮齐鸣,礼花齐放,现场一片欢腾,喜悦的心情绽放在每个人的脸庞。6#焦炉顺利出焦,标志着沙钢焦化三期工程全面竣工投产。焦化三期工程有5#、6#两座焦炉,于2004年2月份开始施工建设。该工程由鞍山焦耐院进行设计,中国一冶负责施工与安装,武汉星宇公司监理。总投
At 9:28 am on June 12, with the first vice president of Sha Steel Group Gongsheng an order: “6 # coke oven push start!” The red coke slowly out of the coke oven. Instant, firecrackers Qi, fireworks in full bloom, the scene a jubilant, happy mood blooming in everyone’s face. 6 # coke oven smoothly out of focus, marking the third phase of Shagang Coking completed and put into operation. Coking Phase III Project 5 #, 6 # two coke oven, started construction in February 2004. The project was designed by Anshan Jiao Naiyuan, China Metallurgical is responsible for construction and installation, supervision of Wuhan Xingyu company. Total investment