摘要:屋面工程质量的好坏直接影响房屋的使用功能,且维修较为困难。为了确保防水的质量,我们将在施工中充分重视该项工作,从材料采购到施工过程的每个环节、每道工序实施严格控制,做到精心施工,特别是各个细部与节点,严格按规范要求施工,确保无渗漏现象发生。为了保证该屋面工程防水施工的质量,我们对屋面工程防水施工质量控制进行了探索,主要包括屋面的施工工艺及质量控制等要点。
关键词:房屋建筑,防水施工,质量控制
Abstract: the engineering quality of roof directly influence building use function, and maintenance more difficult. In order to ensure the quality of the waterproof, we will pay full attention to in the construction of the work, from material purchase to the construction of each link, each procedure implementation of strict control, be careful construction, especially each detail and node, strictly according to the standard requirement construction, ensure no leakage phenomenon. In order to ensure that the roof of the waterproof construction engineering quality, we to roofing project waterproof construction quality control on the exploration, mainly including the roof of the construction technology and quality control points.
Keywords: housing construction, waterproof construction, quality control
中圖分类号: TV523文献标识码:A 文章编号:
1屋面做法:网架屋面板;;1.5厚聚氨酯防水涂料;20厚1:2水泥砂浆找平层;60厚挤塑聚苯板保温层;40厚C15细石混凝土找平层,内配Φ4@150双向单层钢筋网;刷基层处理剂一遍;1.5厚聚氨酯防水涂料;二层1.5厚氯化聚乙烯橡胶共混防水卷材;满铺0.5厚聚乙烯薄膜一层;40厚C30UEC补偿收缩混凝土防水层兼保护层,内配Φ4@150双向单层钢筋网
2组织管理:
2.1指派有经验有能力的工程师主管本工程的防水施工。
2.2 选择有相应施工资质的专业作业队,并报审批。
2.3 严格控制原材料的质量,防水原材料进场必须具备广州市的准用证、出厂质量合格证、材料检验报告。进场前不得开封,进场后开封检查,外观质量也要满足要求。
2.4 由主管工程师组织施工组成员进行施工前的技术交底工作。
2.5 防水工程施工中,过程检查尤为重要。
3 质量控制的措施
3.1 涂膜防水层:
3.1.1施工顺序:
涂膜防水层施工应注意细部构造和各道工序的施工质量。施工顺序为:清理基层→找平层施工完毕,待找平层干燥后→涂刷基层结合剂→细部构造涂刷→涂刷防水涂料,第一遍、待涂层固化后→涂刷第二遍、第三遍防水涂料,直至设计要求厚度→在最后一遍固化之前,防水保护层为水泥砂浆的要在立面上撒上粗砂,以便防水保护层黏结牢固→进行闭水试验或压力水冲洗试验,有渗漏的地方返工;直至无渗漏→防水保护层施工。
3.1.2 作业条件:
基层要求抹平、压光、坚实平整、不起砂并具有一定的强度,阴阳角处抹成圆弧角。基层要求干燥,含水率不超过9%;将基层面上的灰尘、杂物、残留的灰浆硬块清理干净,有突出的部位凿平清净。
3.1.3涂刷施工:
(1)涂刷涂膜防水层时,涂刷的顺序应是先垂直面,后水平面;先阴阳角、细部后大面,而且每一道涂膜防水的涂刷顺序都应相互垂直。
(2)在需要重点处理的细部,要增加一道增强涂布或玻璃丝布,特殊部位如阴阳角处要做尺寸为50mm的聚合物水泥砂浆圆弧,再做附加防水层,宽度为300mm。
(3)涂刷基层处理剂(底胶):基层处理剂涂刷要均匀、充分,且与基层结合牢固。
(4)涂刷第一遍:在底胶干燥固化后,用塑料或橡皮刮板均匀涂刷一层厚约为0.7mm的涂料,涂刮时用力要均匀一致。平面或坡面施工后,在防水层未固化前不应踩踏,采用分区、分片后退法施工。
(5)涂刷第二遍:在第一遍涂膜固化后,对所涂膜的空鼓、气孔、砂、涂层伤痕和固化不良等处进行修补后刮第二遍涂料,涂刮方向与第一遍涂刮方向垂直,厚度控制在0.7mm左右,涂膜顺序先立面后平面。
(6)对未达到设计厚度的,还要进行第三遍涂刷,直至设计要求厚度。
(7)在最后一道涂膜防水层固化前,对于水泥砂浆保护层的要在立面上稀撒粒径约2mm的砂子,再做保护层,以增强涂膜与其保护层的粘结能力。
3.1.4
施工中注意事项:
(1)涂膜防水层施工前,基层一定要清理干净、干燥,否则防水层与基层黏结不牢,防水层容易出现脱落、气泡等缺陷。
(2)涂刷涂膜防水层时要待前一层涂膜固化干燥后进行,并要先检查其上有无残留的气孔或气泡等缺陷;若有时要将缺陷清除,进行修补。
(3)调好的涂料要一次施工完毕,以防止涂料固结,造成浪费。
3.2氯化聚乙烯橡胶共混防水卷材
此产品的施工方法有:粘结法、空铺法、机械固定法三种。接缝一般采用热焊接工艺。本工程采用粘结法,接缝采用热焊接工艺。
(1)粘结法:就是采用胶粘结将卷材直接粘于基层上,粘结法可分为全粘法和局部粘结法两种。全粘法是将卷材与基层全部粘于基层的施工方法。施工时,首先进行卷材预铺,将PVC卷材平整顺直的放置在基层上,纵向搭接宽度为6cm,并进行适当剪裁;横向采用对接处理,其上用20cm-25cm宽的不复合PVC搭接。其次把一卷卷材长边折叠一半(约10cm),从折叠处分别在基层和PVC卷材表面用胶辊涂刷一层胶粘结剂,待胶粘结剂半干燥且不粘手时(约3-4min),使预粘面合伏,用压辊压实,粘好一端,再粘另一端,依次类推,最后接缝用焊枪焊好即可。采用搭接法时,上下层及相邻两幅卷材的搭接缝应错开。
(2)PVC防水卷材的焊接工艺:焊嘴与焊接方向成45度角,压辊与焊嘴平行,并保持一定的间距(大约0.5cm),碾压速度不要太快,小焊嘴(焊嘴宽20mm)一般施焊两道,每道焊接宽度为15-20mm,大焊嘴(焊嘴宽40mm)施焊一道,焊接宽度为25mm(焊接前应强焊一道,宽度不宜太大,目的是为了使施焊时热风不至于溢出,影响施焊质量,焊接边缘应有熔浆溢出,不应出现烧焦现象)。只有保证有效焊接宽度的尺寸,质量才符合要求。
3.2.2找平层施工
(1)在抹找平层前,基层表面清扫干净并洒水润湿,但不能将水浇透,宜适当掌握,以达到找平层与基层能牢固结合为度。
(2)根据坡度要求拉找坡贴灰饼,顺排水方向冲筋,冲筋的间距为1.5M,在排水沟、雨水口处做泛水,冲筋后进行抹找平层。
(3)水层的找平层设分格缝,缝宽20mm,间距不大于6m.分格缝内填密封材料。
(4)砂浆铺设按由远到近、由高到低的程序进行,尽量在每分格内一次连续铺成。施工时严格掌握坡度,采用2m铝合金靠尺找平。
(5)找平层表面压实平整,转角处抹成圆弧形,半径不小于50mm.内部排水的水落口周围亦做成略低的凹坑。
(6)水泥砂浆抹平稍收水后,用抹子进行二次压实抹平。终凝前,轻轻取出嵌缝条。完工后表面尽量少踩踏。
(7)找平层抹平压实后,常温下24小时后洒水养护,养护时间一般不少于7天,要求找平层表面不得有酥松、起砂、起皮现象。干燥后即可进行防水层施工。
3.2.3屋面钢筋网细石混凝土施工
(1)水泥采用强度等级为42.5的普通硅酸盐水泥或硅酸盐水泥,要求为同批产品,不过期,不受潮结块,不得使用火山灰水泥。砂尽量采用中砂,含泥量不大于2%.石子选用料径6~15mm,含泥量不大于1%的洁净、坚硬、级配良好的碎石。水灰不大于0.55.
(2)混凝土搅拌时间不少于2min,要求投料顺序得当,搅拌均匀。混凝土运输过程中注意防止漏浆和离析。
(3)刚性防水层与突出屋面结构的交接处均做柔性密封处理。与天沟、檐沟交接处留凹槽,并用密封材料封严。与女儿墙交接处留设宽30mm的缝隙,并用密封材料嵌填,泛水处铺设卷材或涂膜附加层。
(4)刚性防水层设分格缝,其纵模间距不大于6m,缝宽20~40mm,分格缝内嵌填密封材料,上部铺贴防水卷材。分格缝截面上宽下窄。
(5)细石混凝土防水层中的钢筋网片,施工时放置在混凝土中的上部。
(6)浇捣混凝土时,每个分格块的混凝土一次浇筑完成,不留施工缝。随铺随刮平,并立即用50Kg滚筒辗压或用小功率平板振捣器下衬板振捣一遍。辗压或振捣出浆后,用木板拍实。抹压时不得在表面洒水、加水泥浆或撒干水泥。混凝土收水后进行二次压光。
(7)混凝土面层终凝前,将分格条慢慢取出并修边。混凝土浇筑12~24h后进行养护,养护时间不少于14d,养护初期屋面不得上人。
(8)待屋面面层混凝土养护完毕,分格缝缝内干燥后,用油膏进行嵌缝。
4 施工重點控制措施
4.1防水层的基层处理
水泥砂浆找平层是一种多孔材料,地下水可以通过水泥砂浆层的孔隙上升到地面;地面水也可以通过水泥砂浆层的孔隙渗入地下。基层含水量直接影响防水层与基层的粘结效果。
措施:为了隔绝地下潮湿的上升途径,增加防水涂膜层与基层的粘结力,必须涂刷基层处理剂。基层处理剂的一个重要作用:通过渗入砂浆层的毛细孔,形成一种键合作用,使涂膜防水层很好的粘附于基面上。因此,基层清理的越干净,基层处理剂的渗透越好,物理结合的越好;按照相似相溶原理,基层处理剂与涂料的性质越相似,二者的结合就越可靠。另外对于渗水、冒水严重的地方采取金汤堵漏及堵排结合的措施,再用卷材以湿粘法铺贴防水层。
4.2 防水成品保护
防水层的成品保护往往被忽视,一般情况防水工程交验后防水公司退场,土建公司施工不掌握保护措施,很容易因交叉施工造成防水层受损。
措施:采取切实可行的成品保护措施,安排专人与土建单位配合,在细石砼施工时监督检查防水层的保护工作,防止防水层被破坏,万一出现个别被破坏现象,要及时做好标识,并按规定进行修补。
4.3工程细部构造
工程细部构造包括施工缝、后浇带,穿越防水层的管、孔等,上述部位处理不当,往往是引起渗漏的主要原因。
措施:编制详细的防水构造图,施工中安排熟练的技术工人严格按图施工,各道工序严格把关,并加强与土建工序的配合,保证防水施工质量。
注:文章内所有公式及图表请以PDF形式查看。
关键词:房屋建筑,防水施工,质量控制
Abstract: the engineering quality of roof directly influence building use function, and maintenance more difficult. In order to ensure the quality of the waterproof, we will pay full attention to in the construction of the work, from material purchase to the construction of each link, each procedure implementation of strict control, be careful construction, especially each detail and node, strictly according to the standard requirement construction, ensure no leakage phenomenon. In order to ensure that the roof of the waterproof construction engineering quality, we to roofing project waterproof construction quality control on the exploration, mainly including the roof of the construction technology and quality control points.
Keywords: housing construction, waterproof construction, quality control
中圖分类号: TV523文献标识码:A 文章编号:
1屋面做法:网架屋面板;;1.5厚聚氨酯防水涂料;20厚1:2水泥砂浆找平层;60厚挤塑聚苯板保温层;40厚C15细石混凝土找平层,内配Φ4@150双向单层钢筋网;刷基层处理剂一遍;1.5厚聚氨酯防水涂料;二层1.5厚氯化聚乙烯橡胶共混防水卷材;满铺0.5厚聚乙烯薄膜一层;40厚C30UEC补偿收缩混凝土防水层兼保护层,内配Φ4@150双向单层钢筋网
2组织管理:
2.1指派有经验有能力的工程师主管本工程的防水施工。
2.2 选择有相应施工资质的专业作业队,并报审批。
2.3 严格控制原材料的质量,防水原材料进场必须具备广州市的准用证、出厂质量合格证、材料检验报告。进场前不得开封,进场后开封检查,外观质量也要满足要求。
2.4 由主管工程师组织施工组成员进行施工前的技术交底工作。
2.5 防水工程施工中,过程检查尤为重要。
3 质量控制的措施
3.1 涂膜防水层:
3.1.1施工顺序:
涂膜防水层施工应注意细部构造和各道工序的施工质量。施工顺序为:清理基层→找平层施工完毕,待找平层干燥后→涂刷基层结合剂→细部构造涂刷→涂刷防水涂料,第一遍、待涂层固化后→涂刷第二遍、第三遍防水涂料,直至设计要求厚度→在最后一遍固化之前,防水保护层为水泥砂浆的要在立面上撒上粗砂,以便防水保护层黏结牢固→进行闭水试验或压力水冲洗试验,有渗漏的地方返工;直至无渗漏→防水保护层施工。
3.1.2 作业条件:
基层要求抹平、压光、坚实平整、不起砂并具有一定的强度,阴阳角处抹成圆弧角。基层要求干燥,含水率不超过9%;将基层面上的灰尘、杂物、残留的灰浆硬块清理干净,有突出的部位凿平清净。
3.1.3涂刷施工:
(1)涂刷涂膜防水层时,涂刷的顺序应是先垂直面,后水平面;先阴阳角、细部后大面,而且每一道涂膜防水的涂刷顺序都应相互垂直。
(2)在需要重点处理的细部,要增加一道增强涂布或玻璃丝布,特殊部位如阴阳角处要做尺寸为50mm的聚合物水泥砂浆圆弧,再做附加防水层,宽度为300mm。
(3)涂刷基层处理剂(底胶):基层处理剂涂刷要均匀、充分,且与基层结合牢固。
(4)涂刷第一遍:在底胶干燥固化后,用塑料或橡皮刮板均匀涂刷一层厚约为0.7mm的涂料,涂刮时用力要均匀一致。平面或坡面施工后,在防水层未固化前不应踩踏,采用分区、分片后退法施工。
(5)涂刷第二遍:在第一遍涂膜固化后,对所涂膜的空鼓、气孔、砂、涂层伤痕和固化不良等处进行修补后刮第二遍涂料,涂刮方向与第一遍涂刮方向垂直,厚度控制在0.7mm左右,涂膜顺序先立面后平面。
(6)对未达到设计厚度的,还要进行第三遍涂刷,直至设计要求厚度。
(7)在最后一道涂膜防水层固化前,对于水泥砂浆保护层的要在立面上稀撒粒径约2mm的砂子,再做保护层,以增强涂膜与其保护层的粘结能力。
3.1.4
施工中注意事项:
(1)涂膜防水层施工前,基层一定要清理干净、干燥,否则防水层与基层黏结不牢,防水层容易出现脱落、气泡等缺陷。
(2)涂刷涂膜防水层时要待前一层涂膜固化干燥后进行,并要先检查其上有无残留的气孔或气泡等缺陷;若有时要将缺陷清除,进行修补。
(3)调好的涂料要一次施工完毕,以防止涂料固结,造成浪费。
3.2氯化聚乙烯橡胶共混防水卷材
此产品的施工方法有:粘结法、空铺法、机械固定法三种。接缝一般采用热焊接工艺。本工程采用粘结法,接缝采用热焊接工艺。
(1)粘结法:就是采用胶粘结将卷材直接粘于基层上,粘结法可分为全粘法和局部粘结法两种。全粘法是将卷材与基层全部粘于基层的施工方法。施工时,首先进行卷材预铺,将PVC卷材平整顺直的放置在基层上,纵向搭接宽度为6cm,并进行适当剪裁;横向采用对接处理,其上用20cm-25cm宽的不复合PVC搭接。其次把一卷卷材长边折叠一半(约10cm),从折叠处分别在基层和PVC卷材表面用胶辊涂刷一层胶粘结剂,待胶粘结剂半干燥且不粘手时(约3-4min),使预粘面合伏,用压辊压实,粘好一端,再粘另一端,依次类推,最后接缝用焊枪焊好即可。采用搭接法时,上下层及相邻两幅卷材的搭接缝应错开。
(2)PVC防水卷材的焊接工艺:焊嘴与焊接方向成45度角,压辊与焊嘴平行,并保持一定的间距(大约0.5cm),碾压速度不要太快,小焊嘴(焊嘴宽20mm)一般施焊两道,每道焊接宽度为15-20mm,大焊嘴(焊嘴宽40mm)施焊一道,焊接宽度为25mm(焊接前应强焊一道,宽度不宜太大,目的是为了使施焊时热风不至于溢出,影响施焊质量,焊接边缘应有熔浆溢出,不应出现烧焦现象)。只有保证有效焊接宽度的尺寸,质量才符合要求。
3.2.2找平层施工
(1)在抹找平层前,基层表面清扫干净并洒水润湿,但不能将水浇透,宜适当掌握,以达到找平层与基层能牢固结合为度。
(2)根据坡度要求拉找坡贴灰饼,顺排水方向冲筋,冲筋的间距为1.5M,在排水沟、雨水口处做泛水,冲筋后进行抹找平层。
(3)水层的找平层设分格缝,缝宽20mm,间距不大于6m.分格缝内填密封材料。
(4)砂浆铺设按由远到近、由高到低的程序进行,尽量在每分格内一次连续铺成。施工时严格掌握坡度,采用2m铝合金靠尺找平。
(5)找平层表面压实平整,转角处抹成圆弧形,半径不小于50mm.内部排水的水落口周围亦做成略低的凹坑。
(6)水泥砂浆抹平稍收水后,用抹子进行二次压实抹平。终凝前,轻轻取出嵌缝条。完工后表面尽量少踩踏。
(7)找平层抹平压实后,常温下24小时后洒水养护,养护时间一般不少于7天,要求找平层表面不得有酥松、起砂、起皮现象。干燥后即可进行防水层施工。
3.2.3屋面钢筋网细石混凝土施工
(1)水泥采用强度等级为42.5的普通硅酸盐水泥或硅酸盐水泥,要求为同批产品,不过期,不受潮结块,不得使用火山灰水泥。砂尽量采用中砂,含泥量不大于2%.石子选用料径6~15mm,含泥量不大于1%的洁净、坚硬、级配良好的碎石。水灰不大于0.55.
(2)混凝土搅拌时间不少于2min,要求投料顺序得当,搅拌均匀。混凝土运输过程中注意防止漏浆和离析。
(3)刚性防水层与突出屋面结构的交接处均做柔性密封处理。与天沟、檐沟交接处留凹槽,并用密封材料封严。与女儿墙交接处留设宽30mm的缝隙,并用密封材料嵌填,泛水处铺设卷材或涂膜附加层。
(4)刚性防水层设分格缝,其纵模间距不大于6m,缝宽20~40mm,分格缝内嵌填密封材料,上部铺贴防水卷材。分格缝截面上宽下窄。
(5)细石混凝土防水层中的钢筋网片,施工时放置在混凝土中的上部。
(6)浇捣混凝土时,每个分格块的混凝土一次浇筑完成,不留施工缝。随铺随刮平,并立即用50Kg滚筒辗压或用小功率平板振捣器下衬板振捣一遍。辗压或振捣出浆后,用木板拍实。抹压时不得在表面洒水、加水泥浆或撒干水泥。混凝土收水后进行二次压光。
(7)混凝土面层终凝前,将分格条慢慢取出并修边。混凝土浇筑12~24h后进行养护,养护时间不少于14d,养护初期屋面不得上人。
(8)待屋面面层混凝土养护完毕,分格缝缝内干燥后,用油膏进行嵌缝。
4 施工重點控制措施
4.1防水层的基层处理
水泥砂浆找平层是一种多孔材料,地下水可以通过水泥砂浆层的孔隙上升到地面;地面水也可以通过水泥砂浆层的孔隙渗入地下。基层含水量直接影响防水层与基层的粘结效果。
措施:为了隔绝地下潮湿的上升途径,增加防水涂膜层与基层的粘结力,必须涂刷基层处理剂。基层处理剂的一个重要作用:通过渗入砂浆层的毛细孔,形成一种键合作用,使涂膜防水层很好的粘附于基面上。因此,基层清理的越干净,基层处理剂的渗透越好,物理结合的越好;按照相似相溶原理,基层处理剂与涂料的性质越相似,二者的结合就越可靠。另外对于渗水、冒水严重的地方采取金汤堵漏及堵排结合的措施,再用卷材以湿粘法铺贴防水层。
4.2 防水成品保护
防水层的成品保护往往被忽视,一般情况防水工程交验后防水公司退场,土建公司施工不掌握保护措施,很容易因交叉施工造成防水层受损。
措施:采取切实可行的成品保护措施,安排专人与土建单位配合,在细石砼施工时监督检查防水层的保护工作,防止防水层被破坏,万一出现个别被破坏现象,要及时做好标识,并按规定进行修补。
4.3工程细部构造
工程细部构造包括施工缝、后浇带,穿越防水层的管、孔等,上述部位处理不当,往往是引起渗漏的主要原因。
措施:编制详细的防水构造图,施工中安排熟练的技术工人严格按图施工,各道工序严格把关,并加强与土建工序的配合,保证防水施工质量。