论文部分内容阅读
洛阳市百货大楼工程建筑面积为44100米~2,高68.20米,现浇钢筋混凝土框架剪力墙结构,工程于1991年2月1日开工,1992年12月20日竣工。曾获1994年国家鲁班奖,该工程运用项目法施工,现将具体做法介绍如下。一、组建高效的项目经理部洛阳市百货大楼建立了以公司智力密集型管理层为“龙头”,专业施工企业和农村建筑队为依托,全民与集体、总包与分包、分工协作、互为补充
Luoyang City Department Store has a construction area of 44,100 m2, a height of 68.20 m, and a cast-in-place reinforced concrete frame shear wall structure. The project started on February 1, 1991 and was completed on December 20, 1992. Won the 1994 Luban Award for the State, the project uses the project method of construction, the specific practices are described below. 1. Establishing an efficient project manager department Luoyang City Department Store established the company’s intellectually intensive management as the “leading”, professional construction company and rural construction team as its support, national and collective, general contracting and subcontracting, division of labor and collaboration. To supplement