论文部分内容阅读
【西德《原子经济》1956年第3期第109页报道】西德下萨克森州联邦事务部长就计划中建造的废物调整转形装置回答了议员提问。据他说,目前,西德核燃料后处理公司计划建造一座多用途废物调整转形厂,占地面积约20公顷。该厂的设计与正在进行的示范厂不同,采用了相应的机械技术装备,年处理能力为与350吨乏燃料相当的废物。它的设计是以1981一1984年的其它处置技术计划的研究结果为依据的。
[West Atomic Economy, 1956, No. 3, p. 109] Western Federal Minister of Federal Affairs of Lower Saxony answered the questions raised by the Congress on the waste conditioning device built in the plan. According to him, at present, West Germany’s nuclear fuel reprocessing company plans to build a multi-purpose waste conditioning and transformation plant covering an area of about 20 hectares. The design of the plant is different from the demonstration plant in progress, and the corresponding machinery and equipment are used. The annual processing capacity is equivalent to 350 tons of spent fuel. Its design was based on the findings of other disposal technology plans from 1981 to 1984.