淮河干流正阳关以上扩大行洪通道十大退堤工程的最后一项蒙洼蓄洪区尾部退堤工程,汛前胜利竣工,并顺利通过由水利部淮委、安徽省水利厅等部门专家组成的验收委员会验收,被评为优良工程。该工程为中央基建治淮骨干工程,总投资18845万元,于1997年5月10日正式开工,1999年2月完成主体土方工程,同年底完成附属工程建设,2000年5月10日按计划如期完成铲老堤施工任务。整个工程经过3年奋
Huaihe River is more than the main channel to enlarge the flood channel last ten backwaters project Mengwa flood storage area tail of the backfill project completed before the flood victory and successfully passed by the Ministry of Water Resources Huai Wei, Anhui Provincial Department of Water Resources and other departments Acceptance Committee acceptance, was rated as good works. The project is a key project of central infrastructure construction with a total investment of 188.45 million yuan. It was officially started on May 10, 1997, completed the main earthworks in February 1999, and completed the construction of ancillary works at the end of the same year. On May 10, 2000, according to the plan Completion of the shovel old embankment construction tasks. After three years of the entire project Fen