论文部分内容阅读
小峡水电站计算机监控系统自2004年9月投运以来,因各方面的原因许多功能不能实现,部分功能存在错误或不完善,给监视控制带来较大的不便,也给水电站的安全稳定运行带来隐患。2006年4月,成立了水电站监控完善小组,采用先难后简,先主后次的主导思想,分阶段进行整改,在历经了3 a的奋战之后,取得显著的效果,消除了自投产以来的多项隐患,提高了水电站的自动化运行水平,同时也提高了机电设备的安全可靠性。
Since the computer monitoring system of Xiaoxia Hydropower Station was put into operation in September 2004, many functions can not be realized due to various reasons. Some of the functions are faulty or not perfect, which brings great inconvenience to the monitoring and control as well as safe and stable operation of the hydropower station Bring hidden trouble In April 2006, a group of supervising and controlling hydroelectric stations was set up, adopting the guiding principle of tackling the problem first and then the next and rectifying it in stages. After 3 years of hard work, it achieved remarkable results and eliminated the problems A number of hidden dangers, improve the level of automation of hydropower stations, but also improve the safety and reliability of mechanical and electrical equipment.