本期介绍“分包合同2011版”通用条件第8、9、10、11条的内容。第8条开工和竣工(Commencement and Completion)一、主要内容本条共7款。[8.1]分包工程的开工(Commencement of Subcontract Works)承包商应至少提前14天通知分包商分包合同的开工日期,分包商应在该日期之后尽早开始实施分包工程。[8.2]分包合同竣工时间(Subcontract Time for Completion)分包商应在第10.1款[分包工程的竣工]规定的竣工时间内或者8.4款允许延长的竣工时间内完成分包工
This issue describes the “subcontract 2011 version,” the general conditions of Article 8,9,10,11 of the content. Article 8 Commencement and Completion I. Main Content There are 7 articles in this Article. [8.1] Commencement of Subcontract Works The contractor shall notify the subcontractor of the subcontracting commencement date at least 14 days in advance and the subcontractor shall begin the subcontracting work as soon as possible after that date. [8.2] Subcontract Time for Completion The subcontractor shall complete the subcontracting work within the completion time required by Sub-Clause 10.1 [Completion of Subcontracting] or the Completion Time allowed in Paragraph 8.4