总结了在乌兹别克斯坦开展天然气管道建设项目的前期工作要点:预可研与可研工作、申请总统令、获取路由权、协调国际标准与当地标准差异、调研当地可依托资源、确认技术方案可实施性、降低管道运行维护成本、准确获知当地经济评价参数等。对于国外工程,前期工作应满足属地国政府对工程建设的审批程序和特殊要求,保证技术经济方案在当地资源条件下的可实施性,在充分调研当地公用设施可利用性的基础上,提出工程配套系统技术方案,以保证工程建设内容完整及管道运维安全、经济的要求。
Summarizes the preparatory work points for the gas pipeline construction project in Uzbekistan: pre-feasibility study and feasibility study, application for presidential order, access to the right to route, coordination of international standards and local standards differences, research can rely on local resources to confirm the implementation of technical programs Reduce the cost of pipeline operation and maintenance, and accurately obtain the local economic evaluation parameters. For foreign projects, the preliminary work should meet the approval procedures and special requirements of the government of the territorial government for the project construction, and ensure the implementation of the technical and economic programs under the local resource conditions. Based on the full investigation of the availability of local public facilities, the project Supporting system technical solutions to ensure the integrity of the construction content and pipeline operation and maintenance safety, economic requirements.