论文部分内容阅读
国家重点工程大朝山工程装机总容量135万kW,保证出力363.1MW,多年平均发电量59.31亿kW·h.水库正常蓄水位899m,总库容9.4亿m~3.位于云南省云县与景东交界的澜沧江中下游紧接漫湾工程的又一座梯级电站.坝址距漫湾工程131km,距省会昆明630km.电站枢纽由碾压砼重力坝、右岸地下厂房和长尾水隧洞组成.最大坝高111m,坝顶高程906m,坝
The national key project Dachaoshan project total installed capacity of 1.35 million kW, to ensure that the output of 363.1MW, the average annual generation capacity of 5.931 billion kW · h. The normal reservoir water level of 899m, the total storage capacity of 940 million m ~ 3. Located in Yun County, Yunnan Province and King The middle and lower reaches of the Lancang River at the junction of East China Sea and the next cascade hydropower station in Manwan Bay are 131km away from Manwan Bay and 630km away from Kunming, the capital city of China. The power station consists of a roller compacted concrete gravity dam, a right bank underground powerhouse and a long tailrace tunnel. Dam height 111m, crest elevation 906m, dam