论文部分内容阅读
长沙市公共交通系统工程第一期工程从1983年元月开始,到1984年2月结束,历时13个月.这一阶段的主要任务是:研究长沙市公共交通系统的边界条件和优化目标集;调查和收集系统内部及其环境的有关资料;建立公共交通网络总体模型,并在计算机上实现;寻求多目标优化解;提出优化方案集,并综合进行评价;软技术与硬措施双管齐下,以期最大限度
The first phase of the Changsha Public Transport System Project started from January 1983 and ended in February 1984, which lasted 13 months. The main tasks of this phase were to study the boundary conditions and optimization target set of the Changsha public transport system ; Investigate and collect information about the system and its environment; establish a general model of public transport network and implement it on a computer; seek a multi-objective optimization solution; propose a set of optimized solutions and evaluate them comprehensively; and soft technologies and hard measures go hand in hand Maximum