论文部分内容阅读
石臼所港设计波要素的确定至今尚存在着两种不同的观点。一是认为石港海域产生大浪的波型是纯风浪,其五十年一遇的设计波高为6.9米,相应的设计波周期为8.7秒;另一则认为,石港海域产生大浪的波型是以涌浪为主的混合浪,其五十年一遇的设计波高为7.2米,相应的设计波周期为14.2秒。这两种观点都基于历史天气图推算的结果,
There are two different viewpoints on the determination of design wave elements in Hong Kong. The first is that the waves generated in the Shigang sea area are pure waves. The designed wave height in one 50-year event is 6.9 meters and the corresponding designed wave period is 8.7 seconds. Another is that the wave pattern of large waves generated in the Shigang sea area Is based on the surge-based mixed wave, its 50-year design wave height of 7.2 meters, the corresponding design wave period of 14.2 seconds. Both of these views are based on the results of historical weather map projections,