杨庄滞洪区泄洪闸加固工程于1992年11月18日开工建设,1998年12月通过竣工验收。根据地质钻探资料,闸基主要持力层大都属中硬土层,但在高程56.00~54.50 m范围内夹有1.50~3.00 m厚软土层。闸基建基面高程56.50 m,距软土层顶面仅有0.50~2.00 m。软土层的存在及机械开挖闸基或超挖,使得软土上较薄的持力层变得更薄,严重影响地基的承载能力,且闸室及消力池结构直接坐在软基上。因此,为满足结构对闸基的要求,施工中采用降低水位及自重预压予以地基加固,提高地基强度。加固后的杨庄滞洪区泄洪闸工程至今正常应用。
Yangzhuang detention area flood discharge sluice reinforcement project started construction on November 18, 1992, in December 1998 passed the final acceptance. According to the geological drilling data, most of the main bearing strata of the gate base are medium-hard soil layers, but 1.50-3.00 m thick soft soil layers are sandwiched between elevation 56.00 and 54.50 m. The height of the sluice base is 56.50 m, only 0.50 ~ 2.00 m above the top of the soft soil. The existence of soft soil and mechanical excavation of the gate or over-excavation, making the soft soil thinner bearing layer becomes thinner, seriously affecting the bearing capacity of the foundation, and the sluice chamber and the structure of the weak pool sits directly on the soft foundation on. Therefore, in order to meet the structural requirements of the gate base, the construction of the ground to reduce the water level and gravity preloading to reinforce the foundation to improve the strength of the foundation. Reinforced Yangzhuang flood flood sluice project has been normal application.