论文部分内容阅读
我们在青海省化隆县群科地段的黄河上乙沙尔一级抽水站,采用浮动式抽水囤船.并作了木质、钢质和钢筋混凝土三种结构的船体的方案比较得出:因木船容易腐烂和钢船容易锈蚀,最后选用了长26米,宽7.1米,高1.7米,吃水深度1.3米,排水量为240吨的钢筋混凝土浮动式抽水囤船(简称浮动式).船体结构套用甘肃省刘家峡化肥厂厂外给水工程取水口囤船图纸,混凝土要求强度为300~#,我们仅作了按实际组合的荷载,进行了船体稳定计算和局部修改.
We Qinghai Province Hualong County Branch section of the Yellow River on the Ershaer pumping station, the use of floating pumped storage boat and made of wood, steel and reinforced concrete three hull structure compared to draw: due to Perishable wooden vessels and steel easy to rust, the final selection of 26 meters long, 7.1 meters wide, 1.7 meters high, draft 1.3 meters, displacement of 240 tons of reinforced concrete floating pumped storage boat (referred to as floating). Gansu Province Liujiaxia Fertilizer Plant water supply works outside the factory store drawings, concrete strength requirements of 300 ~ #, we only made the actual combination of load, the stability of the hull calculations and partial changes.