在框架轻板板柱体系中,节点混凝土不仅要求硬化快,早期强度高,而且是决定上层构件安装的关键工序。根据我们实践,如果节点混凝土强度在24小时之内达到200公斤/厘米~2,则主体安装工程就可以大大加快。但是,若采取普通水泥砂浆或混凝土,满足不了施工工期要求,尤其在冬季施工中更满足不了工期要求。即使采取蓄热法、蒸养法、电热法以及掺加化学外加剂等措施,但要在三天内达到设计强度是办不到的,而且还会耗用大量能源,增加设备管线,扩大施工面积,影响其它工种工序的顺利进行。
In the frame light board column system, the joint concrete not only requires quick hardening, but also has high early strength, and is the key process to determine the installation of the upper member. According to our practice, if the concrete strength of the joint reaches 200 kg/cm~2 within 24 hours, the installation of the main body can be greatly accelerated. However, if ordinary cement mortar or concrete is adopted, the construction period requirements cannot be met, and the construction period requirements cannot be met even in winter construction. Even if measures such as heat storage method, steaming method, electrothermal method, and chemical admixture are adopted, it is impossible to reach the design strength within three days, and it also consumes a lot of energy, increases the equipment pipeline, and expands the construction area. , affect the smooth progress of other types of work processes.