珠海横琴二桥主桥主跨400m,钢桁拱梁施工采用拱上吊机结合斜拉扣挂系统的半伸臂架设方法,体系转换频繁,受力复杂。针对其特点,结合施工全过程有限元分析,阐述了通过预偏预降方法实现边墩精确上墩、主拱及刚性系杆无应力快速合龙的施工技术,为同类型钢梁施工提供了有力参考。另外,本桥地处沿海强风地区,上部结构施工经历两个台风期,为检验结构的抗风性能,制作了关键施工工况的缩尺模型,并实施了气弹模型风洞试验。试验结果表明,在检验风速范围内,结构未发生主拱肋颤振、驰振及横向屈曲、扭转发散等静力失稳现象。
Zhuhai Hengqin Bridge main span of 400m, the steel truss arch girder construction using arch hanger combined with oblique pull buckle hanging system half-erection method, the system changes frequently, the force complex. According to its characteristics and combined with the finite element analysis of the whole process of construction, the construction technology of quick closing without piercing on the pier, the accurate arch pier and the main arch of rigid piers and the rigid tie rods is expounded by pre-deflection method. reference. In addition, the bridge is located in strong winds along the coastal areas, the superstructure experienced two typhoon periods, in order to test the wind resistance of the structure, made a key construction conditions scale model, and the implementation of the aeroelastic model wind tunnel test. The experimental results show that there is no static buckling of the main arch ribs, such as the flutter of the main arch rib, chi and lateral buckling, torsion and divergence within the tested wind speed range.