前言 1973年7日阿根廷共和国的国营海罗巴塔哥尼柯矿山公司[HIPASAM(Hierro Patagonicode Sierra Grande)]和三井矿产股份公司签定合同建铁矿选矿厂。下面就该厂的特点和设备情况,建设过程和试运转的经过加以说明。一、简单经过 1972年6月国际投标机构,经过技术审查于同年12月9日签定合同,开设L/C,经政府批准,于1973年7月4日合同正式生效。在1976年6月工厂建成。但因供电系统尚未形成,而不能进行试运转。
Foreword On July 7, 1973, HIPASAM (Hierro Patagonicode Sierra Grande), a state-owned enterprise in the Argentine Republic, signed a contract with Mitsui Mineral Co. to build an iron ore concentrator. The following details of the plant’s characteristics and equipment, construction process and trial run to be explained. First, the simple After June 1972 the international bidding agencies, after technical review in the same year on December 9 signed a contract to open L / C, approved by the government, the contract came into effect on July 4, 1973. In 1976 June factory built. But because the power supply system has not yet formed, and can not be commissioned.