依托盘古大桥体外预应力加固项目,在主梁病害成因分析的基础上,制定了体外预应力加固钢筋混凝土Π梁的设计方案,并对方案进行了详细验算。对体外预应力施加过程中进行了施工监控,并进行了加固后桥梁的成桥试验。研究结果表明:在预应力张拉阶段,主梁的挠度与混凝土应力在安全可控范围内,验证了加固方案的施工可行性;成桥试验结果表明:加固后桥梁的刚度及应力状况得到明显改善,挠度与应力校验系数均在常见值范围内,加固方案达到了预期效果。
Based on the analysis of the causes of the main girders, the design scheme of prestressed reinforcement of reinforced concrete Π beam was established based on the prestressed reinforcement project of Pangu Bridge, and the scheme was checked in detail. During the process of external prestressing, the construction monitoring was carried out and the bridge test of reinforced bridge was carried out. The results show that the deflection of the main girder and the concrete stress are within the safe and controllable range during the prestressed tensioning stage, which verifies the feasibility of the reinforcement scheme. The test results of the bridge show that the stiffness and stress of the bridge are obvious Improvement, deflection and stress check coefficient are within the range of common values, reinforcement program to achieve the desired results.