上海奉贤金汇港桥主桥为中承式提篮拱桥,主桥拱肋为砼边拱肋与钢箱主拱肋两种形式组成,其中钢-混结合段预埋件需与砼边拱肋一同施工,因此施工时钢结构预埋段的定位直接影响了后续钢拱肋安装的精度。同时为了减少对航道的影响,主桥钢结构均考虑采用两台400T履带吊分别位于河道两岸进行单机吊装,施工前结合现场实际情况对机械行走及吊装部位进行合理布置,通过计算得出最不利工况下吊机所需的最大地基承载力,提前进行地基处理,确保吊机在吊装过程中不发生地基失稳的情况。研究成果可对同类工程提供一定的参考。
The main bridge of Fengxian Jinhui Port Bridge in Shanghai is a stern arch bridge, and the main bridge arch rib is composed of concrete side arch rib and steel box main arch rib, of which the embedded part of the steel-concrete combined section should be connected with the concrete side arch rib Together with the construction, the positioning of the embedded section of steel structure during construction directly affects the accuracy of subsequent installation of steel arch ribs. At the same time, in order to reduce the impact on the waterway, the steel structures of the main bridge consider the use of two 400T crawler cranes located on both banks of the river for stand-alone lifting. Before construction, the mechanical walking and hoisting parts are properly arranged according to the actual conditions of the site, Under the conditions of crane crane foundation required for the largest bearing capacity, ground treatment in advance to ensure that the crane hoisting process does not occur when the foundation instability. Research results can provide some reference for similar projects.