摘要:在我国北方特别是东北及内蒙古东部比较寒冷地区,类似电厂、化工厂等大型厂房施工时,为了保证冬季施工项目能正常进行,按建设单位计划全面完成各工程项目的节点工期,并确保冬施项目的工程质量,冬期施工措施的编制显得尤为重要。本文结合东北地区冬季施工过程中目前一些常用的比较成熟的混凝土施工方法简单地从施工条件、施工工艺、施工流程等方面进行了一些介绍。因冬期施工牵涉内容很多,限于篇幅,本文未加详述。
关键词:冬期,混凝土施工及养护,技术
Abstract: in the northeast and especially in the north of eastern Inner Mongolia is cold areas, power plants, and other large chemical plant similar plant construction, in order to ensure the construction project can be carried out as normal winter, the construction unit plan completed the project node period, and ensure the engineering quality; winter project, the construction measures of winter is particularly important. Combining with the northeast area winter construction process at present some commonly used quite mature concrete construction method simply from construction condition, the construction technology, construction process and some paper. For winter construction involves a lot of content, somewhere, this paper has not added detailing.
Keywords: winter, concrete construction and maintenance, technology
中图分类号:TU528 文献标识码:A文章编号:
1 、冬期施工应具备的条件
1.1对搅拌站的供水和供热系统进彻底检修,做好供水供热管道防冻保温措施;骨料堆下暖床供热管道畅通;保证冬施期间搅拌站能够正常工作。
1.2提前做好冬期施工砼及防冻剂的试配试验工作。
1.3根据工程进度及时组织防冻剂和保温材料进场。
1.4做好工地临时供水管道及有关建筑材料的保温越冬保护工作。
1.5在冬期施工到来之前,应对本专业使用的施工机械、设施、劳动保护用品、安全防护设施和存在的不安全隐患进行一次全面的检查,发现不符合项要及时处理,确保冬季施工安全;
1.6施工用电梯属竖直运输设备除按规定定期检查外,在大风雪后还要认真进行全面检查。
1.7在进入冬季施工前,应根据冬季施工特点做好防寒、防火、防冻、防滑和防止煤气中毒工作。注意对取暖设施的全面检查,加强用火管理;
2 冬期施工主要机具及材料
2.1施工主要材料
3 施工主要措施
3.1混凝土施工
3. 1.1搅拌站保温措施
为保证搅拌站冬季正常运行,对搅拌系统(含配料系统、供水系统、搅拌楼、外加剂罐和操作室)采用彩钢板封闭保温。热拌砼所需热水加热方式采用在现有水箱内增设蒸汽管道和加装电加热装置。砼运输车和泵车加装保温被,减少运输和浇筑过程中的热量损失。
3. 1.2砼的配制、搅拌和运输
冬施砼采用综合蓄热法施工,既热拌砼,掺加复合防冻剂,保温蓄热。
A)砼配制:冬施砼配合比,由土建试验室通过试配确定,水泥选用早强型普通硅酸盐水泥,外加剂选用具有防冻、早强、减水和引气作用复合型防冻剂。冬施配比按-10℃及-15℃不同的温度设计,其对应室外最低气温为-15℃及-20℃,当大气温度低于-20℃时,停止混凝土工程施工。
B)混凝土原材料加热采用加热水的方法,水温不超过80°C,水泥不得与80°C以上的水直接接触,以免出现水泥假凝现象。砼搅拌时,先投砂石和热水,搅拌后再投水泥。
C)砂石料:不得含有冰雪等冻结物及易冻裂的矿物质。
D)砼搅拌前,应用热水冲洗搅拌机,搅拌时由专人负责严格掌握防冻剂的掺量,并严格控制砼的水灰比,搅拌时间比常温搅拌时间延长50%,保证砼拌和物的出机温度不低于10℃,入模温度不低于5℃。
E)拌制掺用防冻剂的混凝土,当防冻剂为粉剂时,可按要求掺量与水泥同时投入。
F)砼的运输
冬期施工运输砼拌和物,应使热量损失尽量减少,并采取如下措施:
a.选择最佳的运输路线,尽量缩短运距。
b.对运输砼使用的罐车及泵车加装保温被。
c.合理组织安排运输和卸出砼的工作,应尽量减少砼运输罐车在现场的等候时间。
3. 1.3砼浇筑、养护工程:
A)冬期浇筑的混凝土,其受冻临界强度应符合下列规定:
a.普通混凝土采用硅酸盐水泥或普通硅酸盐水泥配制时,应为设计的混凝土强度标准值的30%。
b.掺用防冻剂的混凝土,当室外最低气温不低于-15°C时不得小于4.0N/mm2,当室外最低气温不低于-30°C时不得小于5.0N/mm2。
c.砼浇筑完成后,表面立即覆盖保温材料,进行保温养护。保温材料采用一层塑料布、两层 (或一层)岩棉被和最外侧一层塑料布的的方法,养护时间不得少于15天。岩棉被必须保持干燥。
d.混凝土浇筑尽量选择在白天气温较高时进行,并立即做好保温养护。
3. 1.4混凝土测温
A)混凝土冬期施工测温项目和次数见下表:
测温项目 测温次数
室外气温及环境温度 每昼夜不少于4次,此外还需测最高、最低气温
搅拌机棚温度 每一工作班不少于4次
水、水泥、砂、石及外加剂溶液温度 每一工作班不少于4次
混凝土出罐、浇筑、入模温度 每一工作班不少于4次
注:室外最高最低气温测量起、止日期为本地区冬期施工起始至终了时止。
B)混凝土养护期间温度测量应符合下列规定:
a.综合蓄热法养护从混凝土入模开始至混凝土达到受冻临界强度,或混凝土温度降到0℃或设计温度以前,应至少每隔6h测量一次。
b.掺防冻剂的混凝土在强度未达到《建筑工程冬期施工规程》JGJ104-97第7.1.1条规定之前应每隔2h测量一次,达到受冻临界强度以后每隔6h测量一次。
c.采用加热法养护混凝土时,升温和降温阶段应每隔1h测量一次,恒温阶段每隔2h测量一次。
d.当测设混凝土的温度降低较快时,可增加保温层的厚度或采取电加热措施。
3. 1.5混凝土试块留置
应按规范规定留置标养试块、结构实体检验试块、同条件养护试块。
3.2建、构筑物暖棚法施工
对于占地面积和高度不大的附属建筑等零米以下基础工程,可以考虑采用暖棚法施工。在结构四周采用苫布搭设防风保温棚,在棚內生火炉和增设电热炉,增加棚内的热源,以保证棚内温度在正温以上。
4 编制依据
4.1《电力工程施工质量检验及评定标准》土建工程篇
4.2《混凝土结构工程施工质量验收规范》GB50204-2002
4.3《建筑工程冬期施工规程》JGJ104-97
4.4《建筑工程施工质量验收统一标准》GB50300-2001
4.5《混凝土质量控制标准》GB50164-92
4.6《混凝土强度检验评定标准》GBJ107-87
4.7《硅酸盐水泥、普通硅酸盐水泥》GB175-1999
4.8《电力建设安全健康与环境管理工作规定》
4.9《电力建设施工及验收规范》SDJ69-87
4.10《电力建设安全健康与环境管理工作规定》
4.11《工程建设标准强制性条文》房屋建筑部分
4.12《电力建设消除施工质量通病守则》
4.13《建筑专业施工组织设计》
结束语 通过以上对冬期施工过程中主要对混凝土施工及养护的描述希望对以后类似的施工起到工程借鉴的作用。
注:文章内所有公式及图表请用PDF形式查看。
关键词:冬期,混凝土施工及养护,技术
Abstract: in the northeast and especially in the north of eastern Inner Mongolia is cold areas, power plants, and other large chemical plant similar plant construction, in order to ensure the construction project can be carried out as normal winter, the construction unit plan completed the project node period, and ensure the engineering quality; winter project, the construction measures of winter is particularly important. Combining with the northeast area winter construction process at present some commonly used quite mature concrete construction method simply from construction condition, the construction technology, construction process and some paper. For winter construction involves a lot of content, somewhere, this paper has not added detailing.
Keywords: winter, concrete construction and maintenance, technology
中图分类号:TU528 文献标识码:A文章编号:
1 、冬期施工应具备的条件
1.1对搅拌站的供水和供热系统进彻底检修,做好供水供热管道防冻保温措施;骨料堆下暖床供热管道畅通;保证冬施期间搅拌站能够正常工作。
1.2提前做好冬期施工砼及防冻剂的试配试验工作。
1.3根据工程进度及时组织防冻剂和保温材料进场。
1.4做好工地临时供水管道及有关建筑材料的保温越冬保护工作。
1.5在冬期施工到来之前,应对本专业使用的施工机械、设施、劳动保护用品、安全防护设施和存在的不安全隐患进行一次全面的检查,发现不符合项要及时处理,确保冬季施工安全;
1.6施工用电梯属竖直运输设备除按规定定期检查外,在大风雪后还要认真进行全面检查。
1.7在进入冬季施工前,应根据冬季施工特点做好防寒、防火、防冻、防滑和防止煤气中毒工作。注意对取暖设施的全面检查,加强用火管理;
2 冬期施工主要机具及材料
2.1施工主要材料
3 施工主要措施
3.1混凝土施工
3. 1.1搅拌站保温措施
为保证搅拌站冬季正常运行,对搅拌系统(含配料系统、供水系统、搅拌楼、外加剂罐和操作室)采用彩钢板封闭保温。热拌砼所需热水加热方式采用在现有水箱内增设蒸汽管道和加装电加热装置。砼运输车和泵车加装保温被,减少运输和浇筑过程中的热量损失。
3. 1.2砼的配制、搅拌和运输
冬施砼采用综合蓄热法施工,既热拌砼,掺加复合防冻剂,保温蓄热。
A)砼配制:冬施砼配合比,由土建试验室通过试配确定,水泥选用早强型普通硅酸盐水泥,外加剂选用具有防冻、早强、减水和引气作用复合型防冻剂。冬施配比按-10℃及-15℃不同的温度设计,其对应室外最低气温为-15℃及-20℃,当大气温度低于-20℃时,停止混凝土工程施工。
B)混凝土原材料加热采用加热水的方法,水温不超过80°C,水泥不得与80°C以上的水直接接触,以免出现水泥假凝现象。砼搅拌时,先投砂石和热水,搅拌后再投水泥。
C)砂石料:不得含有冰雪等冻结物及易冻裂的矿物质。
D)砼搅拌前,应用热水冲洗搅拌机,搅拌时由专人负责严格掌握防冻剂的掺量,并严格控制砼的水灰比,搅拌时间比常温搅拌时间延长50%,保证砼拌和物的出机温度不低于10℃,入模温度不低于5℃。
E)拌制掺用防冻剂的混凝土,当防冻剂为粉剂时,可按要求掺量与水泥同时投入。
F)砼的运输
冬期施工运输砼拌和物,应使热量损失尽量减少,并采取如下措施:
a.选择最佳的运输路线,尽量缩短运距。
b.对运输砼使用的罐车及泵车加装保温被。
c.合理组织安排运输和卸出砼的工作,应尽量减少砼运输罐车在现场的等候时间。
3. 1.3砼浇筑、养护工程:
A)冬期浇筑的混凝土,其受冻临界强度应符合下列规定:
a.普通混凝土采用硅酸盐水泥或普通硅酸盐水泥配制时,应为设计的混凝土强度标准值的30%。
b.掺用防冻剂的混凝土,当室外最低气温不低于-15°C时不得小于4.0N/mm2,当室外最低气温不低于-30°C时不得小于5.0N/mm2。
c.砼浇筑完成后,表面立即覆盖保温材料,进行保温养护。保温材料采用一层塑料布、两层 (或一层)岩棉被和最外侧一层塑料布的的方法,养护时间不得少于15天。岩棉被必须保持干燥。
d.混凝土浇筑尽量选择在白天气温较高时进行,并立即做好保温养护。
3. 1.4混凝土测温
A)混凝土冬期施工测温项目和次数见下表:
测温项目 测温次数
室外气温及环境温度 每昼夜不少于4次,此外还需测最高、最低气温
搅拌机棚温度 每一工作班不少于4次
水、水泥、砂、石及外加剂溶液温度 每一工作班不少于4次
混凝土出罐、浇筑、入模温度 每一工作班不少于4次
注:室外最高最低气温测量起、止日期为本地区冬期施工起始至终了时止。
B)混凝土养护期间温度测量应符合下列规定:
a.综合蓄热法养护从混凝土入模开始至混凝土达到受冻临界强度,或混凝土温度降到0℃或设计温度以前,应至少每隔6h测量一次。
b.掺防冻剂的混凝土在强度未达到《建筑工程冬期施工规程》JGJ104-97第7.1.1条规定之前应每隔2h测量一次,达到受冻临界强度以后每隔6h测量一次。
c.采用加热法养护混凝土时,升温和降温阶段应每隔1h测量一次,恒温阶段每隔2h测量一次。
d.当测设混凝土的温度降低较快时,可增加保温层的厚度或采取电加热措施。
3. 1.5混凝土试块留置
应按规范规定留置标养试块、结构实体检验试块、同条件养护试块。
3.2建、构筑物暖棚法施工
对于占地面积和高度不大的附属建筑等零米以下基础工程,可以考虑采用暖棚法施工。在结构四周采用苫布搭设防风保温棚,在棚內生火炉和增设电热炉,增加棚内的热源,以保证棚内温度在正温以上。
4 编制依据
4.1《电力工程施工质量检验及评定标准》土建工程篇
4.2《混凝土结构工程施工质量验收规范》GB50204-2002
4.3《建筑工程冬期施工规程》JGJ104-97
4.4《建筑工程施工质量验收统一标准》GB50300-2001
4.5《混凝土质量控制标准》GB50164-92
4.6《混凝土强度检验评定标准》GBJ107-87
4.7《硅酸盐水泥、普通硅酸盐水泥》GB175-1999
4.8《电力建设安全健康与环境管理工作规定》
4.9《电力建设施工及验收规范》SDJ69-87
4.10《电力建设安全健康与环境管理工作规定》
4.11《工程建设标准强制性条文》房屋建筑部分
4.12《电力建设消除施工质量通病守则》
4.13《建筑专业施工组织设计》
结束语 通过以上对冬期施工过程中主要对混凝土施工及养护的描述希望对以后类似的施工起到工程借鉴的作用。