晃桥水库工程石料填筑工程合同量11444m~3,招标投标过程中,坝料称呼前后矛盾;原开挖利用料10万m~3(3万m~3直接上坝,7万m~3二次倒运上坝)由于坝料变更(质量要求提高)而无料可用;Ⅱ号料场岩石级别升高;原覆盖层9.8万 m~3摊入单价,由于坝料要求提高等原因覆盖层及无用料总量将达60万 m~3左右。这些需要认真研究合同,找出证据,提出合理的索赔要求。
In the process of bidding and tendering, the dam material is contradictory both before and after. The original excavation and utilization materials of 100,000m 3 (30,000m 3 direct upper dam and 70,000m 3 Secondary down the dam) due to dam material changes (quality requirements increase) and no material available; Ⅱ No. yard rock level increased; the original cover 98,000 m ~ 3 into the unit price, due to dam material requirements to improve the cover And the total amount of non-use materials will reach 600,000 m 3. These require careful study of contracts, identification of evidence, and reasonable claims.