1 工程概况 天楼地枕水电站是长江一级支流清江干流上的一座中型引水式电站(以下简称天电),由恩施州水电勘测设计院勘测设计,1993年建成投产,现已运行8年多。电站取水坝控制来水面积1906 km~2,最大取水流量56.0m~3/s,右岸6. 45 km引水渠道引水至车坝发电,渠道设计引用流量42.0m~3/s,发电流量38.56m~3/s,设计水头 80.2 m,装机容量 2.52 MW,多年平均发电量1.34亿 kWh。
1 Project Overview Tiantiadi Hydropower Station is a medium-sized diversion power station (hereinafter referred to as Tiandian) on the mainstream of the Qingjiang River, a tributary of the Yangtze River. It was surveyed and designed by Enshi Hydropower Survey and Design Institute and put into operation in 1993 and has been in operation for over 8 years . Hydropower station take control of the dam area of 1906 km ~ 2, the maximum water flow of 56.0m ~ 3 / s, the right bank 6. 45 km diversion canal water diversion to the car dam power generation, channel design reference flow 42.0m ~ 3 / s, power flow 38.56m ~ 3 / s, design head 80.2 m, installed capacity 2.52 MW, the average annual generation capacity of 134 million kWh.