对某黄河岸边取水水源地进行勘察评价,为某基地提供必要的水源地。我队承担该项工程,从84年1月提交设计,4月投入生产,经过11个月的钻探施工,于85年2月业已竣工,可以提交日出水量15万吨的供水水源地,达到了预期的目的,并为水源地的二期工程即详勘打下了良好的基础。一、水文地质主要技术要求水源地位于某地区以南,黄河岸边东侧,与黄河一岸之隔。属某洪积扇河漫滩地域。为了保证国家重点工程按质按量按期完成,提出主要技术要求是:1.在查明区域水文地质条件的基础上进行某洪积扇河漫滩及Ⅰ、Ⅱ级阶地的水文地质勘探。主要勘
Conduct survey and appraisal on the water intake source of a certain Yellow River bank and provide the necessary water source for a certain base. Our team undertook the project, submitted the design from January, 84 and put it into production in April. After 11 months of drilling construction, it was completed in February of 85th and can submit a water supply source of 150,000 tons of water a day The expected purpose, and for the second phase of the water source that is a detailed survey laid a good foundation. First, the main technical requirements of hydrogeology Water source is located in a region south of the Yellow River east of the shore, separated from the Yellow River. Is a alluvial fan floodplain area. In order to ensure that key national projects are completed on schedule according to the quality and quantity, the main technical requirements are as follows: 1. On the basis of ascertaining regional hydrogeological conditions, hydrogeological exploration of a floodplain flood plain and grade I and II terraces will be carried out. Main survey