一、工程概况石泉水电站,位于汉江上游陕西省石泉县以上1公里处。以发电为主,同时兼有发展航运、灌溉、渔业等综合效益。水电站枢纽工程,右岸为混凝土空腹重力坝,左岸为混凝土重力坝,最大坝高65米,坝顶全长353米,总库容4.7亿米~3。左岸设坝后厂房,安装3台4.5万千瓦机组,总装机容量13.5万千瓦,年平均发电
First, the project profile Shiquan Hydropower Station, located in the upper reaches of Han River, Shiquan County, Shaanxi Province, 1 km above. Mainly to power generation, both the development of shipping, irrigation, fisheries and other comprehensive benefits. The right bank is a concrete fast-loading gravity dam, the left bank is a concrete gravity dam, the maximum dam height is 65 meters, the total length of the crest is 353 meters, and the total storage capacity is 470 million m3. Dam on the left bank of the plant, the installation of three 45,000 kilowatts units, with a total installed capacity of 135,000 kilowatts, the average annual power generation