6个月,122个工作日,45个加班日,资源高峰时20个人全力以赴,在公司及有关领导的支持下,在合理分配工作和实时的进度监控调度下,东风新能源项目在4月6日顺利上线,结果好于客户预期,在非常有限的时间内完成这样一个复杂的项目,客户业务部门负责人称此项目为奇迹。此项目时间之紧、任务之重、复杂度之高,在公司历来的MES项目中都不多见,在此对该项目进行回顾总结,以期对后续的项目管理有所帮助。
6 months, 122 working days and 45 overtime days. At the peak of resources, 20 people went all out. Under the support of the company and the leaders concerned, with reasonable allocation of work and real-time schedule monitoring and control, Dongfeng New Energy Project under 4 The successful launch on the 6th of the month, the result is better than the customer expected, in a very limited time to complete such a complex project, the head of customer business unit called the project a miracle. This project time is tight, the task is heavy, the complexity is high, is rare in company’s historical MES project, reviews the project in this summary, hopes to the subsequent project management to be helpful.