4月13日,国网四川省电力公司组织召开玉瓦水电站及送出工程启动验收会议。与会委员听取了电站及送出工程各方关于机组启动有关情况的汇报。会议同意玉瓦水电站1号、2号机组和送出工程具备启动试运行条件,待黑河塘变电站启动后,即可开展电站并网试验和72 h试运行工作。在玉瓦水电站主体工程建设过程中,九寨沟公司根据工程形象面貌及时开展各项验收的组织和协调工作,各阶段验收未
April 13, State Grid Sichuan Electric Power Company organized a Yuwa hydropower station and send out the project to start the acceptance meeting. The participating members listened to the reports of the power station and the sending parties concerned about the start of the unit. The meeting agreed Yuva Hydropower Station Unit 1, Unit 2 and send out the project have started trial operation conditions, to be Heihetang substation start, you can carry out power station grid test and 72 h trial operation. In the process of construction of the main project of Yuwa Hydropower Station, Jiuzhaigou Company timely conducted the organization and coordination of all acceptance according to the engineering image, and the acceptance of each phase