论文部分内容阅读
千里之外的金沙江水,由溪洛渡左岸电厂化作滚滚电能,经四川、贵州、江西、湖南,直奔浙江。浙江人民对此期待已久。电网建设者们则在溪洛渡左岸—浙江金华±800千伏特高压直流输电工程的建设现场,用实际行动回应这份期待。从2012年8月1日正式破土动工,建设者们历经严寒与酷暑,克服重重困难,用不足两年的时间,建设了一条由西而东
Thousands of miles away from the Jinsha River, from the left bank power plant Xiluodu into rolled power, by Sichuan, Guizhou, Jiangxi, Hunan, went straight to Zhejiang. Zhejiang people have long been looking forward to this. Power grid builders are on the left bank of Xiluodu - Zhejiang Jinhua ± 800 kV HVDC transmission project construction site, with practical action to respond to this expectation. From August 1, 2012 formally broke ground, builders who have experienced severe cold and summer heat, to overcome numerous difficulties, with less than two years, built a from west to east