【日本《读卖新闻》2014年9月17日报道】日本核燃料公司(JNF)计划将六所村(Rokkasho)乏燃料后处理厂的竣工日期延后至2016年春季。该公司原计划在2014年10月完成六所村后处理厂的建设,但日本原子力规制委员会(NRA)已表示,这座工厂的安全检查工作需要耗费的时间比最初预想的更长。目前在位于日本各地的核电厂中贮存着总计约1.7万吨乏燃料。日本经济产业
Japan Yomiuri Daily News, September 17, 2014 Japan Nuclear Fuel Company (JNF) plans to postpone the completion date of the Rokkasho spent fuel reprocessing plant until the spring of 2016. The company originally planned to complete the Rokkasho-ku reprocessing plant in October 2014, but Japan’s atomic force regulatory committee (NRA) has said the safety inspection at the plant will take longer than initially envisaged. There are currently a total of about 17,000 tons of spent fuel stored in nuclear power plants located throughout Japan. Japan’s economic industry