一个施工企业一般都同时承担若干个单位工程的施工。如果只在其中一个工程上应用统筹法,其他工程一律给它让路,使这个工程享有特殊优越的物质技术条件,那么,尽管在这一个工程上可能会取得良好的经济效益,全局的经济效益却不一定好;如果每个工程各搞一套,在每个工程的局部上都似乎筹划得很好,在整个企业的全局上则可能互相矛盾、互相冲突,这样也难于卓有成效地发挥统筹法的作用。我们必须积极推行大统筹,至少要在一个独立核算的施工单位范
A construction company generally assumes the construction of several unit projects at the same time. If only one of the projects is applied to the overall planning method, other projects will always give way to it, so that this project enjoys special superior material and technological conditions. Then, although this project may achieve good economic benefits, the overall economic benefits It is not necessarily good; if each project is carried out one by one, it seems that there is a good plan for each part of the project. The overall situation of the entire enterprise may be conflicting and conflicting with each other. It is also difficult to effectively implement the unified law. effect. We must actively implement large-scale pooling, at least in an independent accounting construction unit