论文部分内容阅读
本局一九五○年工作计划,经各单位展开讨论后,复具体制订了四、五、六三个月份的工作计划。兹简要分述如下:甲、道路工程(一)新兴方面:本年新兴道路工程原计划为灌油路八条,面积八二、二五九平方公尺,至六月底拟完成三九、五九八平方公尺,占全年48%强;洋灰路一条,面积一二、四一一平方公尺,泼油路二条(内一条加泼灌油路第三遍油),面积六、四一二平方公尺,至六月底完成;碴石路二条,共三○、六二○平方公尺,六月底以前完成二○○○平方公尺,占百分之二·四;修建侧石七条,共一五九八○公尺;六月底以前完成五八六五公尺,占百分之三九;六月底以前修建津盐公路;在塘大修路八六○○平方公尺。本年度新兴工程自四月一日先后开工,共分五组分别施工,一组北马路两段,西马路;一组老铁桥街,沿河马路,南马路东段,袜子胡同;一组是大沽路,地道大街;一组是六纬路,新开路,新货厂路;一组是埋设南开二纬路、新开路等七条路的侧石。
After the work plan of 1950 for this Council was discussed by the various departments, the work plan for the next four, five and six months was elaborated. A brief summary is as follows: A. Road construction (I) Emerging aspects: In this year, the newly-emerged road works are originally planned to be eight filling roads with an area of 8,295 square meters. By the end of June, 399 and 59 Eight square meters, accounting for 48% of the annual strong; a gray road, an area of twelve, four hundred and eleven square meters, pouring two oil routes (within a third plus pouring oilfield), area six, four one Two square meters, to be completed by the end of June; ballast stone two, a total of three, six hundred and two square meters, completed by the end of June 2000 square meters, accounting for two percent; , A total of 159,000 meters; completed by 5,865 meters before the end of June, accounting for 39%; by the end of June before the construction of Tianjin Salt Road; pond overhaul 8,600 square meters. The newly-started project of this year has started operation on April 1 in total and is divided into five groups, one in each of the two blocks of North Road and the West Road; one in Old Iron Bridge Street, Yanhe Road, the eastern section of South Road and the sock alleys; Dagu Road, authentic Avenue; a group of Liuwei Road, a new road, a new factory road; a group is buried Nankai two latitude, the new open seven road side stone.