金堆城钼矿始建于1958年。目前矿山已基本达到二期投产要求,采场工作线达到6300米,两级矿量保有月数分别达到14.5个月和8个月,主要运输干线路基已形成,有些已作了路面。二期建设速度虽然没有达到设计投产时限,但由于抓紧企业管理,抓好一期生产促进二期建设,使生产和建设少发生干扰,使一期
Jinduicheng molybdenum mine was founded in 1958. At present, the mine has basically reached the second phase of production requirements, stope line to 6300 meters, two levels of mine retention months respectively reached 14.5 months and 8 months, the main trunk of the transport road has been formed, and some have been paved. Although the construction speed of the second phase did not reach the design and production deadline, as a result of stepping up the management of the enterprise, we should pay close attention to the first phase of production to promote the second phase of construction so as to make the production and construction less disruptive and the first phase