本试验工程系一饭店建筑,面积6447平方米,主楼总高33米,为九层框架结构,并有地下室一层。整个工程面临施工场地狭小、工期紧张的困难。为了提前竣工,我们在结构阶段进行了多种施工方案比较,最后选定了“先安后浇法”施工工艺。事实证明用先安后浇法施工不仅克服了施工场地小的困难,而且比计划工期提前了42天,整幢大楼结构施工有效工期为176天,平均每层不到20天,取得了良好的经济效益。施工质量也得
The test project is a hotel building with an area of 6,447 square meters. The main building has a total height of 33 meters. It is a nine-story frame structure and has a basement floor. The entire project faces the difficulties of narrow and narrow construction sites. In order to complete the work ahead of schedule, we conducted a variety of construction plans during the construction phase. At the end, we selected the “safety first injection method” construction process. The facts show that the use of Xian’an post-cast construction not only overcomes the difficulties of the construction site, but also is 42 days earlier than the planned construction period. The construction period of the entire building structure is 176 days, with an average of less than 20 days per floor. It has achieved good results. Economic benefits. Construction quality also got