目前国内污水处理厂建设的主要特点是前期投资额大而回报周期长,通常其回报期在十年以上。污水厂建设作为建设工程中一项普通而又特殊的工程项目,成本控制首当其冲,也是各个做污水处理投资企业重点考虑的项目。论文通过对崇仁污水厂建设的实例研究、对污水处理厂建设成本各个阶段现状的阐述和对各阶段成本控制存在问题的分析,找到污水处理厂建设成本各个阶段控制的措施及建议。从而为其它及今后类似污水处理厂建设成本控制提供参考及建议。
At present, the main feature of the construction of domestic sewage treatment plants is the large amount of previous investment and long return period, usually with a return period of more than 10 years. Sewage treatment plant construction as an ordinary and special construction projects, the cost control bear the brunt, but also do all the sewage treatment investment enterprises to consider the key projects. Through the research on the construction of Chongren Wastewater Treatment Plant, this paper expounds the current situation of each stage of the construction cost of sewage treatment plant and analyzes the existing problems of cost control in each stage, and finds out the measures and suggestions for the control of each stage of the construction cost of the sewage treatment plant. So as to provide reference and suggestions for other and future similar sewage treatment plant construction cost control.