在安排任何工程计划时,总是希望在满足既定的条件下,按照一定的目标寻求最优方案。如在工期一定的情况下,要求投入的人力、材料、设备和资金等资源数量为最小的方案;或是在最低工程成本的条件下,寻求工期最短的方案;或是在工期最短的条件下,寻求成本最低的方案等。应用微机进行“工期—成本”优化的最小断集法之目的就在于寻求以上各种最优方案。本文根据割集的基本理论应用微机由网络的完全关联矩阵求出网络在不同工期下的最小断集,同时考虑各活动之间的相互制约关系,对计划网络活动的持续时间逐步调整,最终实现在不同
When arranging any project plan, it is always hoped that the best plan will be pursued according to certain goals under the established conditions. If the construction period is fixed, the amount of resources such as manpower, materials, equipment and capital required to be invested shall be the minimum; or the scheme with the shortest construction period shall be sought under the conditions of the minimum project cost; or the condition with the shortest construction period , seek the lowest cost program, etc. The purpose of applying the computer-based minimum cut-off method for “construction period-cost” optimization is to seek the above various optimal solutions. In this paper, according to the basic theory of cut-set, the computer uses the complete correlation matrix of the network to find the minimum disconnection of the network under different durations. At the same time, considering the mutual constraints between each activity, the duration of the planned network activity is gradually adjusted and finally realized. in difference