按预定能力生产(Run (a) Rate)是对供应商生产过程是否能以报价生产能力生产出合格产品的现场实际验证。其目的是通过该程序能识别出不能满足产量要求的零部件,从而降低在开始批量生产时的失败风险。也是验证供应商的生产制造过程是否能满足顾客合同要求的工装能力(最高生产能力MCR)、SGM的产量要求(正常生产能力LCR)及顾客提出的质量要求。 最高生产能力(Maximum Capacity Rate)(MCR)表示供应商最大生产能力,包括休息日加班,它不需要增加投资和增添设备。通常,最高生产能力比正常生产能力高
Production (Run (a) Rate) is an on-the-spot verification of whether a supplier’s production process can produce a qualified product at quoted production capacity. The purpose is to identify the parts that can not meet the production requirements through this procedure, thereby reducing the risk of failure when starting mass production. It is also to verify whether the supplier’s manufacturing process meets the customer’s contract requirements of the tooling capacity (maximum production capacity MCR), SGM production requirements (normal production capacity LCR) and customer quality requirements. Maximum Capacity Rate (MCR) indicates the maximum capacity of a supplier, including overtime on a rest day. It does not require additional investment and additional equipment. Normally, the highest production capacity is higher than normal production capacity