近几年来,我们合理地采用顶升工艺完成了几项技术改造工程。在这些改造工程施工中,不仅避免了大量的毁坏性拆除,而且节省了大量的施工机具和建筑材料,使整个施工过程文明、简单、安全、可靠。一、浓缩槽工程概况株洲冶炼厂浮银尾砂9号浓缩槽为钢筋混凝土圆形结构。槽体内径18m,壁厚250mm,槽顶标高为9.213m。槽体顶部为一圈由12节拼接而成的高
In recent years, we have rationally adopted the lifting technology to complete several technological transformation projects. In the construction of these renovation projects, not only a large number of destructive demolitions are avoided, but also a great deal of construction equipment and building materials are saved, making the entire construction process civilized, simple, safe and reliable. First, the concentration of the tank project Overview Zhuzhou Smelter Fuxing Tailing 9 concentration tank is a circular structure of reinforced concrete. The inner diameter of the tank is 18m, the wall thickness is 250mm, and the elevation at the top of the tank is 9.213m. The top of the tank is a circle made of 12 joints