湖南省欧阳海水库是以灌溉为主结合发电的大型水利水电工程。水库流域面积5409km~2,总库容4.24亿m~3,大坝百年设计水位130m。为充分发挥工程效益,1992年安装了水文自动测报系统。该系统由北京水利自动化研究所设计安装,当年5月正式投入使用。该系统使用两年多来,收到了明显的经济效益,主要有两个方面: a.减少了洪水造成的水库下游淹没损失。使用该系统后,可实时采集到库区各个雨量遥测
Ouyanghai Reservoir in Hunan Province is a large-scale water conservancy and hydropower project based on the combination of irrigation and power generation. Reservoir basin area of 5409km ~ 2, with a total storage capacity of 424000000 m ~ 3, dam a hundred years design level 130m. In order to give full play to project benefits, in 1992 to install a hydrological automatic reporting system. The system was designed and installed by Beijing Institute of Water Conservancy and officially put into use in May of that year. The system has been used for more than two years and has received obvious economic benefits. There are two main aspects to the system: a. Redundant losses caused by flooding downstream of reservoirs have been reduced. After using the system, real-time acquisition of all rainfall in the reservoir telemetry