1 工程概况伽师县英阿瓦提分水枢纽工程是克孜河上的一座主要渠首工程 ,主要任务是泄洪和灌溉引水。工程位于伽师县西北部夏普吐勒乡克曼村境内 ,距喀什市 5 0公里 ,离伽师县城 2 5公里。该工程于 1 987年建成 ,由分水闸和溢流堰两部分组成 ,分水闸设计引水流量为 90立方米每
1 Project Overview Jiashi County British Awati Water Diversion Project is a major drainage project on the Kizi River, the main task is to flood and irrigation diversion. The project is located in Kham Village, Sharp Tulle Township, northwest of Jiashi County, 50 kilometers away from Kashi City and 25 kilometers away from Jiashi County. The project was completed in 1987, by the sluice and overflow weir in two parts, sub-sluice design diversion flow of 90 cubic meters per