论文部分内容阅读
石洞口电厂位于吴淞口上游13.5公里,在长江口南支河段的下端,毗邻宝钢原料码头(图1)。一期工程为120方千瓦,每年需500万吨煤由海轮进口;二期工程后为240万千瓦,共有950万吨煤进口。 在石洞口地区建设煤码头有以下几个特点:
Shidongkou Power Plant is located 13.5 kilometers upstream of Wusongkou. At the lower end of the Nanzijian section of the Yangtze River estuary, it is adjacent to Baosteel Raw Materials Terminal (Figure 1). The first phase of the project is 120 square kilowatts, requiring 5 million tons of coal to be imported by the seagoing vessels each year; and 2.4 million kilowatts after the second phase with a total of 9.5 million tons of coal imports. Construction of coal pier in Shidongkou area has the following characteristics: