论文部分内容阅读
在2013年压力管道元件制造许可证评审工作中,压力管道元件制造企业在取换证的申请准备过程、体系运行过程、资源条件和质量保正手册编制过程中,存在下列主要问题。一、申请准备过程中存在的主要问题1、没有及时收集和认真学习国家有关许可证管理的法规标准,也没有组织有关人员研究布置许可证取换证有关工作,造成准备工作不充分。2、申请换证提前时间不够六个月,换证受理后再联系进行型式试验和现场鉴定评审以及问
In the review of the manufacturing license for pressure piping components in 2013, the following major problems existed in the process of preparation of application documents, system operation process, resource conditions and quality assurance manuals for pressure piping component manufacturers. First, the main problems in the process of application preparation 1, did not collect timely and carefully study the national regulatory standards for permit management, nor did the relevant personnel to study the layout permit replacement certificate related work, resulting in inadequate preparation. 2, apply for renewal less than six months in advance, after renewal of the admissibility and then contact type testing and field assessment review and ask