山东莱芜粉末冶金厂,1995年生产海绵铁12000t,铁粉5000t,为进一步适应市场需求,推进企业发展,于1996年2月26日实施“万吨铁粉改造工程”,工程计划工期65天。主要改造项目包括:自行制造一台四管还原电炉;新增2台振动球磨机、2台氨分解炉(每台30m~3)及其它相应配套机电设施。届时,该厂将拥有还原电炉4台(9管),振动球磨机4台,氨分解能力120m~3。
Shandong Laiwu Powder Metallurgy Plant produced 12,000 tons of sponge iron and 5,000 tons of iron powder in 1995. In order to further meet the market demand and promote the development of the enterprise, the project of “10,000 tons of iron powder renovation project” was implemented on February 26, 1996, and the construction schedule is 65 days. Major transformation projects include: to create a four-reduction furnace; add two vibration ball mill, two ammonia decomposition furnace (each 30m ~ 3) and other corresponding mechanical and electrical facilities. By then, the plant will have reduction furnace 4 (9 tubes), vibrating ball mill 4, ammonia decomposition capacity 120m ~ 3.