某工程为大跨度人字形钢桁架结构,跨度为43.6米,共10榀屋架,每榀6吨,平面尺寸为52×43.6米。本工程施工时具有下列特点:其一、工程地处山坡之下,三面都有建筑物,其间隔只能通过劳动车,仅一面有狭窄空地,可供施工场地布置。再则屋架跨度大,刚度小,安装有困难。为此我们改变了传统的安装方法,采取屋架山吊车起吊,高空行走的方案,其方法简述如下: (一)起吊 1.起吊前,在屋架的两端安装行走轮,
A project is a large-span herringbone steel truss structure with a span of 43.6 meters, a total of 10 roof trusses, 6 tons per cull, and a plane size of 52 x 43.6 meters. The construction of this project has the following characteristics: First, the project is located below the slopes and has buildings on three sides. The interval can only pass through the labor vehicle. Only one side has a narrow open space and can be used for the construction site layout. In addition, the truss span is large, its rigidity is small, and installation is difficult. To this end, we have changed the traditional installation method and adopted the roof crane crane to lift and walk at high altitude. The method is briefly described as follows: (1) Lifting 1. Before lifting, install running wheels at both ends of the roof truss.