对水电站设备在工地发生二次倒运的费用问题,目前各水电设计部门及有关单位对此有不同的理解,很多设计部门在编制投资概算时都未考虑此项目和费用。但实际上,对一个中型以上的电站而言,其设备的二次倒运费用,往往还是一笔不小的数目。有人认为,能源部、水利部1989年颁发的《水利水电工程设计概(估)算费用构成及计算
With regard to the cost of the secondary dumping of the hydropower station equipment on the construction site, the various hydropower design departments and related units have different understandings of this, and many design departments did not consider this item and the cost when preparing the investment estimate. However, in fact, for a medium-sized or more power station, the cost of the secondary dumping of its equipment is often a small sum. Some people think that the composition and calculation of the “General Estimates for Designing (Evaluation) Funds for Water Conservancy and Hydropower Projects issued by the Ministry of Energy and Ministry of Water Resources in 1989