论文部分内容阅读
辽宁省某成套设备公司杨秀文问: 1994年,我公司承接了一项成套设备的出口任务,同年11月9日,我公司与哈尔滨市某金属机械加工厂签订工矿产品购销合同一份,约定其为我公司制作大型油膜轴承二套,总价款230万元,1995年5月20日前交货,我公司在货到后10日内验收付款,如供方不能交货或需方中途废止合同,按15%支付违约金,逾期交货或逾期付款的,每日按万分五支付违约金。合同签订后,即1995年的3月份,哈市加工厂突然发来电函,告知我方因技术问题不能按期履行合同,要求延期4个月。因为该产品是出口设备,出口合
Yang Xiuwen, a complete set of equipment company in Liaoning Province Q: In 1994, our company undertook the export mission of a complete set of equipment. On November 9 of the same year, our company signed a purchase and sales contract of industrial and mining products with a metal mechanical processing factory in Harbin. The company produced two sets of large oil film bearings, the total price of 2.3 million yuan, May 20, 1995 delivery, the company within 10 days after receipt of payment acceptance, such as the supplier can not be delivered or the demand side of the abolition of the contract , According to 15% pay liquidated damages, late delivery or overdue payment, daily payment of liquidated damages. After the signing of the contract, that is, March 1995, Harbin City, suddenly sent a letter to inform us that due to technical problems can not be fulfilled on schedule, requiring an extension of 4 months. Because the product is export equipment, exports together