2010年,串列加速器升级工程在线同位素分离器(ISOL)的建造工作按计划进行,主要进展如下。1靶源测试台架作为ISOL系统靶源研制的重要平台,2010年完成了靶源测试平台的研制。靶源测试平台与ISOL束线前端基本一致,包括四极透镜、六级透镜、多极透镜、分析磁铁、束流检测单元等ISOL束线的组成部件,不仅用于靶源的测试、完善,也是ISOL系统投入运行后对辐射活化较严重的前端进行模
Construction of Tandem Accelerator Upgrades Online Isotope Separator (ISOL) was carried out on schedule in 2010 with the following major developments. A target source test bench as an ISOL system target source developed an important platform in 2010 to complete the target source test platform development. The target source test platform is basically the same as the front end of the ISOL beam line. The components of the ISOL beam line including the quadrupole lens, the six-level lens, the multipole lens, the analysis magnet and the beam current detection unit are not only used for testing, ISOL system is also put into operation on the radiation activation of more serious front-end mode